City of Ashvale: Brightmoor's response for the Riverside footbridge renewal
Our bid to design and rebuild the Riverside footbridge with the river path open on weekdays, a 14-month programme, and a single named engineer accountable from survey to handover.
Read the executive summary- Tender reference
- ASH-2026-114
- Submission deadline
- 28 November 2026, 12:00
- Contract type
- Design and build
- Bid lead
- Marcus Adeyemi
Rebuild the footbridge in 14 months without closing the river path on weekdays
The City asked for a replacement footbridge that keeps the riverside cycle route usable during works and lasts 120 years with low maintenance. Brightmoor proposes a weathering-steel bridge assembled off-site and lifted into place over two weekend closures.
Weekday access stays open through a temporary crossing 40 metres downstream, already discussed with the Ashvale cycling forum during the site visit.
- Two weekend closures instead of a six-week shutdown
- Off-site fabrication to cut on-site noise
- One named engineer from survey to handover
Proposed programme from contract award to the bridge opening, including the design stage and two weekend lifts.
Our answers to the five evaluation criteria in section 4 of the RFP
Each answer follows the order and weighting of the City's scoring matrix. Open one to read the full response.
4.1 Technical approach (30%)
We will survey the existing abutments in the first month and reuse them if load tests confirm their capacity. The new deck is a weathering-steel box girder that needs no repainting.
The full method statement is in the file library as document 3.
4.2 Programme and phasing (20%)
Design takes four months, fabrication runs in parallel with abutment works, and the two lifts are scheduled for weekends outside the summer events calendar the City shared.
4.3 Public access and communication (20%)
A temporary crossing keeps the cycle route open on weekdays. Residents get two weeks' notice of each weekend closure through the City's newsletter and on-site signs.
4.4 Social value (15%)
Two engineering apprenticeships for Ashvale residents and a site open day for local schools during fabrication.
4.5 Price (15%)
Our fixed-price offer and the schedule of rates are in the commercial envelope, as required by section 6. They are not published on this microsite.
Every mandatory requirement in the RFP and where we answer it
| Ref. | Requirement | Status | Where to find it |
|---|---|---|---|
| M1 | Professional indemnity insurance of at least the required amount | Compliant | File library, document 6 |
| M2 | Design life of 120 years for the main structure | Compliant | Criterion 4.1 |
| M3 | Weekday access for pedestrians and cyclists during works | Compliant | Criterion 4.3 |
| M4 | Environmental management plan for works near the river | Compliant | File library, document 4 |
| M5 | Completion within 15 months of contract award | Compliant: 14 months | Criterion 4.2 |
| M6 | Use of a local supply chain for at least half of subcontracts | Partially met: clarification requested | Q&A log, question 3 |
Three footbridge projects similar to the Riverside renewal
- Footbridge
Millstream crossing
Replacement of a 1960s concrete footbridge with a steel span lifted in one weekend.
- Cycle route
Canal towpath bridges
Three small crossings rebuilt while the towpath stayed open through temporary diversions.
- Heritage
Station footbridge refurbishment
Strengthening of a listed footbridge with new steelwork hidden inside the original frame.
Fictional projects, shown to illustrate the case study tile.
The named team that would deliver the Riverside footbridge
-
Marcus Adeyemi
Bid lead and project directorAccountable for the contract from award to handover and the City's single point of contact.
-
Elin Lindqvist
Lead bridge engineerOwns the structural design and signs off both lifts.
-
Rosa Castellano
Community liaisonRuns resident notices, the cycling forum meetings, and the school open day.
-
James Whitcombe
Environmental managerPrepares the river works plan and leads the weekly environmental checks.
Fictional people. Initials stand in for the portrait or video tile a live microsite would show.
Seven tender documents in the order the City's portal lists them
- 1. Signed form of tenderPDF · 3 pages
- 2. Technical responsePDF · 38 pages
- 3. Method statement and lifting planPDF · 22 pages
- 4. Environmental management planWord · 16 pages
- 5. Programme (Gantt export)Excel · 1 tab
- 6. Insurance certificatesPDF · 4 pages
- Full submission packZIP · 6 files
Sample file tiles. In a live microsite each one opens in the document viewer or downloads, and every open is tracked.
Questions and answers exchanged with the City during the tender
Q1, 14 October 2026: Can the temporary crossing use the City's land on the north bank?
City answer: yes, subject to a licence that the City will issue at contract award.
Q2, 21 October 2026: Are weekend closures allowed in July?
City answer: no. July weekends are reserved for the riverside festival.
Q3, 4 November 2026: Does the local supply chain requirement count materials or only subcontracts?
Awaiting the City's answer. Our compliance matrix shows M6 as partially met until it arrives.